Leading Through Operational Disruption
How centralized resource management, proactive communication, and decisive leadership sustained three specialized service lines through an eight-day hurricane outage and helped establish a more resilient operating model.

The Challenge
In 2024, Hurricanes Helene and Milton created significant operational challenges for a creative services organization with critical production capabilities concentrated in St. Petersburg, Florida.
Although contingency preparations had been made in anticipation of the storms, the St. Petersburg operation ultimately became unavailable for eight days. This disrupted the normal management and production structure supporting three specialized, US-restricted service lines:
USG: Creative services supporting government studies.
USD: Creative services supporting aerospace and defense contractors.
USPD: Presentation design services for clients with contractual US data-localization requirements.
Each service line operated through its own established workflow, using different tools, procedures, and dedicated resources. These systems were effective under normal conditions and intentionally separated to accommodate their distinct operational and client requirements.
The disruption, however, created a challenge those systems had not been designed to address.
A substantially reduced pool of eligible resources now needed to support all three service lines simultaneously, with no consolidated mechanism for evaluating competing priorities, balancing capacity, or coordinating assignments.
As the manager outside the affected location with the necessary access and visibility across all three service lines, I assumed responsibility for coordinating their operations while continuing to oversee my existing teams.
The immediate objective was to maintain essential services, preserve client confidence, and manage limited capacity without compromising the distinct requirements of each service line.
Establishing a Unified Operating Model
The first priority was creating a consolidated view of operational demand.
Under normal conditions, each service line independently tracked incoming requests, assignments, deadlines, available capacity, and production status. During the outage, these separate systems made it difficult to compare priorities across the organization.
For example, one service line might have ten nonessential requests awaiting production while another had a single business-critical request. Without a unified view, the relative importance of those requests could not be evaluated effectively against the same limited resource pool.
I developed an Excel-based tracking system that standardized the essential operational information across all three service lines.
The system consolidated incoming requests, business priorities, resource availability, assignments, deadlines, and production status into a single management view.
Importantly, it did not replace the established workflows or eliminate the separation between service lines. Instead, it provided an additional coordination layer that enabled informed prioritization and resource allocation across the operation while respecting existing client and access restrictions.
This allowed decisions to be driven by business criticality rather than the volume of work within any individual queue.
Setting Expectations and Maintaining Confidence
Recognizing that normal turnaround times would not be achievable with reduced resources, I established a clear communication strategy on the first day of the outage.
Out-of-office messages across all three service lines acknowledged the disruption, advised clients that delivery times could be longer than usual, and reinforced that requests were being actively monitored by leadership outside the affected area.
I also established an expectation that every incoming request would receive an acknowledgment, even when production could not begin immediately.
This distinction was deliberate. While delivery capacity was constrained, communication and accountability did not need to be.
Throughout the disruption, all three service lines maintained a 100% response rate within two hours, ensuring that clients knew their requests had been received and were being managed.
To maintain leadership visibility, I also issued two comprehensive operational updates each day, one at opening and another at closing.
These updates kept stakeholders informed about the state of the operation, evolving priorities, production performance, and outstanding challenges, supporting informed decisions throughout the outage.
Maintaining Delivery Under Constrained Capacity
With consolidated tracking and communication protocols established, the focus shifted to balancing available resources against changing business priorities.
Assignments were evaluated across all three service lines, taking into account urgency, business impact, deadlines, resource availability, and applicable operational restrictions.
Not every request could receive its normal turnaround time. Work was deliberately prioritized to protect critical commitments while maintaining visibility and accountability for requests that needed to wait.
Despite the significant reduction in available resources, all three service lines remained operational every day throughout the eight-day outage.
The operation maintained a 70% same-day completion rate, alongside its 100% response rate within two hours.
These results reflected a deliberate balance between production performance, transparent communication, and responsible allocation of constrained resources.
Protecting Critical Business Priorities
The hurricane disruption also threatened a time-sensitive recruiting initiative for a new Team Leader position.
With the original interview panel unavailable because of the storm, delaying the process would have triggered a mandatory three-month hiring delay.
To prevent that outcome, I assumed direct ownership of the recruiting process while coordinating the operational continuity response.
I personally conducted 12 first- and second-round interviews involving internal and external candidates, coordinating supplemental support from international colleagues where appropriate.
All interviews took place during the eight-day outage.
The recruiting process was completed on schedule and resulted in a successful hire, avoiding the three-month delay and protecting an important organizational staffing priority.
This demonstrated the importance of maintaining focus on longer-term business needs, even while responding to an immediate operational crisis.
Recovery and Operational Stabilization
When the St. Petersburg location reopened, the organization needed to transition from its temporary operating model back to normal production.
The centralized visibility and coordinated management practices established during the outage supported that transition.
Full operational stabilization was achieved within two hours of reopening.
The unified tracking system had also demonstrated value beyond the immediate emergency. The returning St. Petersburg team recognized its benefits, and the approach continued to be used temporarily after normal operations resumed.
What began as a practical response to constrained resources had revealed opportunities for greater coordination across service lines.
From Emergency Response to Organizational Resilience
The experience became a catalyst for broader business continuity improvements.
The operating approach developed during the outage served as a foundation for a comprehensive business contingency plan. Building on the lessons learned, the organization examined the gaps exposed by the disruption and developed additional safeguards against similar events.
One important change involved reducing the geographic concentration of operational leadership. Additional leadership capacity was developed in Arizona rather than continuing to concentrate those responsibilities in St. Petersburg, creating resources that could be leveraged in future contingency scenarios.
Although I did not author the formal contingency plan, I served as an advisor during its development and reviewed the final plans before implementation.
The experience also helped demonstrate the value of greater coordination between previously separate production environments. Alongside other operational developments, including expanded opportunities to share design resources, this contributed to the eventual consolidation of two production environments.
That subsequent consolidation was led by others, but the initial response helped establish the operational foundation for greater integration.
The Results
The initiative delivered measurable results during the crisis and contributed to longer-term organizational improvements.
​​​​​​​100% response rate within two hours across all three service lines throughout the outage.
70% same-day completion rate despite significantly reduced production capacity.
Eight consecutive days of operational continuity across all three specialized service lines.
Full operational stabilization within two hours of the St. Petersburg location reopening.
12 recruiting interviews completed, resulting in a successful hire on schedule and avoiding a mandatory three-month delay.
Twice-daily leadership communications maintaining visibility and accountability throughout the disruption.
A unified resource management approach that informed subsequent business continuity planning and helped establish a foundation for greater operational integration.
Leadership Insights
This experience reinforced several principles that extend beyond crisis management.
Effective systems are designed for specific operating conditions. The existing service-line workflows were efficient and appropriate under normal circumstances. The disruption required an additional management capability, not the wholesale replacement of systems that were already working.
Prioritization requires a common view of business impact. When resources become constrained, the number of requests in a queue is less important than their relative urgency and consequences. Standardizing operational information made those distinctions visible and actionable.
Communication is a critical component of business continuity. Even when normal delivery expectations cannot be maintained, consistent acknowledgment, transparency, and accountability preserve confidence in the operation.
Immediate crises cannot be allowed to create avoidable future problems. Protecting the recruiting timeline prevented an eight-day disruption from creating an additional three-month staffing delay.
Recovery should lead to greater resilience. The most valuable outcome was not simply restoring normal operations. It was using the experience to identify vulnerabilities, inform future contingency planning, and help create a more adaptable organizational structure.
The objective was never to pretend the disruption had no consequences. It was to maintain control of the operation, protect the most important business commitments, and ensure that the organization emerged better prepared for the next challenge.